I-15 Widening and Devore Interchange Reconstruction

Description: In San Bernardino County at and near the I-15/I-215 interchange. Construct one lane in each direction on I-15 from Glen Helen Parkway through the Interchange, reconfigure interchange and add truck by

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City
Zip Code 92407
 
Senate District
23
Assembly District 33, 47
Congressional District 08, 31
 
Caltrans District
08
 
 
County/State Route San Bernardino 15
Postmile Begin/End 14 16
 
County/State Route San Bernardino 215
Postmile Begin/End 16 17.8
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  4196    2,602  
Peak Period Time Savings (minutes)  24167    14,362  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Dennis Saylor (909)884-8276   dsaylor@sanbag.ca.gov
Design (PS&E) Phase
Caltrans Dennis Saylor (909)884-8276   dsaylor@sanbag.ca.gov
Right of Way Phase
SANBAG Dennis Saylor (909)884-8276   dsaylor@sanbag.ca.gov
Construction Phase
Caltrans Dennis Saylor (909)884-8276   dsaylor@sanbag.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$53,743 $0 $53,743
Non-bond Funding
State/Federal*
$129,010 $0 $129,010
Local**
$141,707 $905 $142,612
Non Budgeted ETC
$0 $0 $0
 
Total**** $324,460 $905 $325,365

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$10,295 $0 $10,295 $6,175
Design(PS&E)
$6,580 $0 $6,580 $0
Right of Way
$55,106 $-13,229 $41,877 $33,515
Construction
$252,479 $14,134 $266,613 $258,488
 
Total* $324,460 $905 $325,365 $298,178

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/04/2009 

02/29/2012 
 

 
03/04/2009 

02/29/2012 
100  03/04/2009 

02/29/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/15/2012 

 
 

 
11/15/2012 

 
100  11/13/2012 

 


Begin Right of Way Phase

End Right of Way Phase
03/01/2012 

04/30/2014 
 

 
03/01/2012 

04/30/2014 
100  02/29/2012 

04/29/2016 


-24 
Begin Construction Phase

End Construction Phase
11/15/2012 

03/25/2016 
 

 
11/15/2012 

03/25/2016 
75  10/15/2012 

11/17/2017 


-20 
Begin Closeout Phase

End Closeout Phase
03/25/2016 

02/28/2019 
 

 
03/25/2016 

02/28/2019 
100  11/17/2017 

11/01/2022 
-20 

-45 
Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 4196 2,602
Peak Period Time Savings (minutes) 24167 14,362

Bond Funding Cost
Adopted:
$53,743,000
Current Approved:
$53,743,000
Actual Expenditures:
$53,364,000

 

Status as of December 31, 2023.