Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
I-15 Widening and Devore Interchange Reconstruction |
Description: In San Bernardino County at and near the I-15/I-215 interchange. Construct one lane in each direction on I-15 from Glen Helen Parkway through the Interchange, reconfigure interchange and add truck by
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | |
Zip Code | 92407 |
Senate District |
23 |
Assembly District | 33, 47 |
Congressional District | 08, 31 |
Caltrans District |
08 |
County/State Route | San Bernardino 15 |
Postmile Begin/End | 14 16 |
County/State Route | San Bernardino 215 |
Postmile Begin/End | 16 17.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 4196 | 2,602 |
Peak Period Time Savings (minutes) | 24167 | 14,362 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Dennis Saylor | (909)884-8276 | dsaylor@sanbag.ca.gov | |
Design (PS&E) Phase |
Caltrans | Dennis Saylor | (909)884-8276 | dsaylor@sanbag.ca.gov | |
Right of Way Phase |
SANBAG | Dennis Saylor | (909)884-8276 | dsaylor@sanbag.ca.gov | |
Construction Phase |
Caltrans | Dennis Saylor | (909)884-8276 | dsaylor@sanbag.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$53,743 | $0 | $53,743 | ||||
Non-bond Funding | |||||||
State/Federal* |
$129,010 | $0 | $129,010 | ||||
Local** |
$141,707 | $905 | $142,612 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $324,460 | $905 | $325,365 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$10,295 | $0 | $10,295 | $6,175 | |||
Design(PS&E) |
$6,580 | $0 | $6,580 | $0 | |||
Right of Way |
$55,106 | $-13,229 | $41,877 | $33,515 | |||
Construction |
$252,479 | $14,134 | $266,613 | $258,488 | |||
Total* | $324,460 | $905 | $325,365 | $298,178 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
03/04/2009 02/29/2012 |
|
03/04/2009 02/29/2012 |
100 | 03/04/2009 02/29/2012 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/15/2012 |
|
11/15/2012 |
100 | 11/13/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
03/01/2012 04/30/2014 |
|
03/01/2012 04/30/2014 |
100 | 02/29/2012 04/29/2016 |
0 -24 |
|
Begin Construction Phase
End Construction Phase |
11/15/2012 03/25/2016 |
|
11/15/2012 03/25/2016 |
75 | 10/15/2012 11/17/2017 |
1 -20 |
|
Begin Closeout Phase
End Closeout Phase |
03/25/2016 02/28/2019 |
|
03/25/2016 02/28/2019 |
100 | 11/17/2017 11/01/2022 |
-20 -45 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 4196 | 2,602 |
Peak Period Time Savings (minutes) | 24167 | 14,362 |
Bond Funding Cost | |
---|---|
Adopted: |
$53,743,000 |
Current Approved: |
$53,743,000 |
Actual Expenditures: |
$53,364,000 |
Status as of December 31, 2023.